Our work was part of the GMT 355 project at General
Motors Assembly Plant in Shreveport, LA. It involved the construction of
an elevated conveyor trestle that connects the new Body Shop as well as
completion of All Trades work for the new General Assembly building. The
new conveyor enclosure extends over seven bays of the existing Assembly
Building and was constructed by extending the existing main building
columns and adding a new floor and roof structure. Significant work on
this project occurred during the plant's summer shut-down period and
involved modifying the existing roof purlins with new floor beams.
Doster received the following award for this project:
2002 ABC Excellence in Construction Award for the Alabama
Chapter and Mid-Tennessee Chapters |
General Motors Corporation
Truck Plant Expansion
Shreveport, Louisiana
Client
General Motors Corporation
Warren, Michigan
Architect
Harley Ellis
Southfield, Michigan
Construction Cost
$4,500,000
Completion Date
June 2002 |