Doster was chosen from a selected bidders list to
construct this new auto parts and distribution center in Orlando. The
design/build project features concrete tilt-up construction, and
includes a 425,000 square foot warehouse and 50,000 square feet of
office space. After four months of design, the project was built in 12
months.
Doster won the
following awards for this project:
2001 ABC
National Exellence in Construction Award
2001 ABC Excellence in
Construction Award
2001 AGC Build Central Florida Award
|
DaimlerChrysler Corporation
Mopar Parts Distribution Center
Orlando, Florida
Client
DaimlerChrysler Mopar Division
Center Line, Michigan
Architect
Gresham Smith & Partners
Birmingham, Alabama
Construction Cost
$19,400,000
Completion Date
September 2001 |