Doster Construction Company was selected to be the
General Contractor for this three-story, 117,000 square foot, 283-space
concrete parking garage. The structure is a mixture of cast-in place
concrete and pre-stressed beams/joists, and has an architectural precast
panel-facade.
This is the first project of a major expansion to Winter Haven's
existing campus for which Doster Construction Company has been selected
as the Construction Manager.
Doster received the following award for this project:
2006 ABC Excellence in Construction Award |
Winter Haven Hospital Parking Deck
Winter Haven, Florida
Client
Winter Haven Hospital
Winter Haven, Florida
Architect
Harvard Jolly, Inc.
Tampa, Florida
Construction Cost
$5,500,000
Completion Date
December 2006 |